Bardsir Steel Project – TAM Iran Khodro

Client:
TAM Iran Khodro Company
Main Client:
Bardsir Steel Company
Start Date:
2013–2014
Scope of Work:
Fabrication, packing, transportation, and installation of locally manufactured equipment and steel structures including Silo, Mixing Chamber, Air Cooler, and Main Bag House (approx. 750 tons). Fabrication and installation of ducting and support structures for the flue-gas treatment system (approx. 1,000 tons). Installation of mechanical equipment, steel structures, and water-cooled ducts (approx. 270 tons). Material supply, fabrication, and installation of lime-carbon silo and its steel structure (approx. 80 tons). Installation of supplementary steel structure components for the melting shop building (approx. 370 tons). Foundation handover inspection, shim placement (padding), erection, alignment, grouting, bolt tightening, torque adjustment, and handover of heavy and light steel structures for the project’s main buildings (approx. 1,100 tons).